This
example corresponds to a Jobshop (Jobshop
scheduling) problem, having three jobs (A,B,C)
that must be executed sequentially in three
steps (1,2,3), but not all jobs require
all the stages, meaning that the jobs will
be executed in a subset of stages. The processing
time for each stage is given by the following
table:
| Job/stage |
1 |
2 |
3 |
| A |
5 |
- |
3 |
| B |
- |
3 |
2 |
| C |
2 |
4 |
- |
The
objective is to obtain the sequence of task,
which minimizes the completion time T. In
order to obtain a feasible solution the
clashes between the jobs must be eliminated.
For more details about this formulation
see Raman
& Grossmann (1994).
LogMIP
input file for this example |